New updated PB0-100 questions and answers

PB0-100 braindumps Description
Questions and Answers:115 Q&As

Updated: 2009-09-11
Exam Number/Code: PB0-100
Exam Name: APC NCPI Design

APC APC PB0-100 115Q&As are created by senior IT lecturers in Certinside certification Q&A network and APC product experts combination PROMETRIC or VUE true-to-date environmental examination of the original title.
The Questions & Answers cover the latest real test and with all the correct answer.we promise the Q&A for APC PB0-100(APC NCPI Design) examination of original title complete coverage.PB0-100 Questions & Answers help you pass the exam.

  • Share/Bookmark
Posted in APC. Comments Off »

New updated DU0-001 questions and answers

DU0-001 braindumps Description
Questions and Answers:243 Q&As

Updated: 2009-09-14
Exam Number/Code: DU0-001
Exam Name: Data Center University Associate Certification

APC APC DU0-001 243Q&As are created by senior IT lecturers in Certinside certification Q&A network and APC product experts combination PROMETRIC or VUE true-to-date environmental examination of the original title.
The Questions & Answers cover the latest real test and with all the correct answer.we promise the Q&A for APC DU0-001(Data Center University Associate Certification) examination of original title complete coverage.DU0-001 Questions & Answers help you pass the exam.

  • Share/Bookmark
Posted in APC. Comments Off »

New updated PB0-200 questions and answers

PB0-200 braindumps Description
Questions and Answers:115 Q&As

Updated: 2009-09-07
Exam Number/Code: PB0-200
Exam Name: APC NCPI Design

APC APC PB0-200 115Q&As are created by senior IT lecturers in Certinside certification Q&A network and APC product experts combination PROMETRIC or VUE true-to-date environmental examination of the original title.
The Questions & Answers cover the latest real test and with all the correct answer.we promise the Q&A for APC PB0-200(APC NCPI Design) examination of original title complete coverage.PB0-200 Questions & Answers help you pass the exam.

PB0-200 Free Demo Download


Certinside offers free demo for PB0-200 115 Q & As with Expert Explanations). You can check out the interface, question quality and usability of our practice exams before you decide to buy it.


Download PB0-200 Exam Pdf Demo

Download PB0-200 Exam iEngine Demo

 
 
Exam : APC PB0-200
Title : APC NCPI Design

1. Which two products are appropriate for an IT network wiring closet? (Choose two.)
A. single-phase UPS
B. 800 amp DC rectifier
C. 4-post open frame rack
D. 10kVA three-phase UPS
E. 15-ton computer room air conditioner
Answer: AC

2. What is a common application for 2-post racks?
A. telecom
B. server room
C. remote office
D. IT data center
Answer: A

3. If a company requests that its UPS output power be distributed to the racks through an isolation transformer, what are they trying to do?
A. decrease the cable size to the load
B. increase the efficiency of the system
C. increase availability throughout the data center
D. prevent electrical noise from locking up the servers
Answer: D

4. You have specified that a 1000 VA rack-mount UPS solution be added to your client’s existing data center. Considering the size of the UPS, which service product is appropriate?
A. Load Bank
B. Thermography
C. Extended Warranty
D. Preventive Maintenance
Answer: C

5. A company has a 30kW N+1 InfraStruXure solution in their small data center. In the event of a power module failure, it wants e-mail notification that there is a loss of redundancy. The only connection is a LAN connection for monitoring. What should you do?
A. using the InfraStruXure Manager, connect into the RJ45 port and configure the e-mail notification feature
B. using an Out of Band Management Card, connect into an external modem and configure the e-mail notification feature
C. using the serial port on the UPS, connect the UPS solution to a desktop computer and configure the e-mail notification feature
D. using the Building Management Card, connect the UPS solution to the facility Building Management software and configure the e-mail
notification feature
Answer: A

6. Click the Calculator button. A medium-size data center has been retrofitted and the new IT equipment requires 39kW at a power factor 0.90. The existing UPS system is 40kVA. Which two actions should you take? (Choose two.)
A. keep the actual UPS system: 40kVA means 40kW
B. replace the diesel generator to cover the extra load
C. replace the actual UPS system with a minimum 45kVA
D. check the entire UPS installation to make sure it is able to support the new load
Answer: CD

7. A site requires redundant power feeds to single-corded servers. What is a possible redundant configuration?
A. two single-module UPSs feeding one rack-mount Automatic Transfer Switch and one outlet strip per rack
B. two single-module UPSs each feeding dual-panel distribution boards, which in turn feed two outlet strips per rack
C. two single-module UPSs each feeding two outlet strips per rack; plugging half the servers in one strip and the other half in another strip
D. two single-module UPSs each fed from separately derived utility sources; sources that come from one of two independent utility substations
Answer: A

8. How do you achieve full system redundancy in a precision air conditioning system?
A. install multiple air conditioning systems in an N+1 configuration
B. install a properly-sized DX air cooled unit with chilled water back-up
C. install a properly-sized air conditioning unit with redundant compressors
D. install Building System cooling (comfort cooling) with an air conditioning unit in standby
Answer: A

9. A remote office for a small business has 20 employees. Its IT equipment supports four file servers, e-mail, storage, and Internet access. Which three products are appropriate for this office’s IT room that has no IT staff? (Choose three.)
A. 30kW N+1 UPS
B. 12kVA N+1 UPS
C. 4-post rack
D. 15-ton computer room air conditioner
E. remote security and environmental monitoring
Answer: BCE

10. What are two reasons why a fully rated UPS (output kW = output kVA) is more compatible with today’s IT loads than an 80%-rated UPS (output kW = output kVA at a 0.8 power factor)? (Choose two.)
A. 80%-rated UPSs are more efficient.
B. Today’s IT loads are power-factor corrected.
C. Fully-rated UPSs have superior output voltage control.
D. Fully-rated UPSs make it less likely to undersize the UPS.
E. Today’s IT loads lock up when powered by an 80%-rated UPS.
Answer: BD

11. An IT manager wants one hour of UPS runtime on a Voice over IP (VoIP) solution that will be located in a small wiring closet. To get the full hour of runtime and continuous operation, what else must be in place?
A. The closet must have sufficient cooling for that period.
B. Shutdown software should be loaded on the VoIP server.
C. The UPS must be oversized in wattage to provide this runtime.
D. The equipment must be installed in a full enclosure for proper security.
Answer: A

12. What is the most accurate way to determine the capacity of an existing standby generator?
A. ask the facility manager
B. calculate 30% over the UPS capacity
C. look at the generator name plate in the genset room
D. calculate capacity based on the load the generator is powering
Answer: C

  • Share/Bookmark